Tungamah Pipeline Project

360km

Pipelines

42

Weeks to Build

140ml

Earthen Storage

1

Pump Station

The scope of work included construction of 360km of pipelines ranging in diameter size from 50mm to 300mm, supplied by Iplex Pipelines. The works also included construction of a 140 megalitre earthen storage lagoon and an automated remote controllable multi-component pump station.

A major challenge on the project from the outset was the resistance of several key Landowners to joining the scheme threatening to derail the project. Face to face meetings between the Landowners and Managing Director Wayne Mitchell established Landowner consent for the 40km of pipelines to be constructed through their properties, with access points omitted pending resolution of Water Authority issues.

Project Details

  • 360km of pipelines 300-50mm in diameter
  • 1 automated remote controllable multi-component Pump station, including buildings, mechanical, electrical and software
  • 140 ML Earthen Lagoon
  • Manage Landholder Liaison
  • Survey, design and As-Constructed plans
  • Commissioning, provision of Operating Manuals and Training

LOCATION

Tungamah, VIC

PROJECT VALUE

12m

YEAR

2006

CLIENT

Goulburn Murray Water

Related Projects

Goulburn Murray Water

Tungamah Pipeline Project

Santos Limited

Santos Pre-field Development

The Narrabri project, although short in length and duration was very challenging due to the alignment of the pipeline being the middle of the Pilliga State Forrest, within an existing HDPE Water line corridor, with no new clearing allowed. The pipeline was subject to strict EIS conditions including minimising dust and erosion onsite. To manage the conditions an extensive erosion sediment control plan (ESCP) was designed and implemented.